Preliminary Bid Results

Preliminary Bid Opening Results are posted on this site as raw price data, and are subject to further verification and validation for responsiveness and other evaluations. The listed apparent low bidder may not be the vendor awarded the contract. Note: These preliminary bid opening results are not listed in Bid/RFP sort order.

  • General Solicitations
    (Goods/Services/Miscellaneous)
  • Construction Solicitations
  • World Trade Center Solicitations
Contract/
Solicitation
Bid Due Date Contract Title/Solicitation Description
54998 12-Dec-2018

Supply and Deliver Contactor for PATH PA-5 Railcar Condenser Fan

55103 15-Nov-2018

Hydrants and Accessories – Two (2) Year Requirements Contract

54962 15-Nov-2018

Provision of Cisco Branded Hardware/Software Smartnet Maintenance Services – Requirement Contracts

55096 14-Nov-2018

Assorted Coveralls and Arc Flash Apparel – Two (2) Year Requirements Contract

55040 13-Nov-2018

Supply and Delivery of Foundations for Guidance Signs– Delivery to John F. Kennedy Airport

54781 09-Nov-2018

Supply and Deliver Four (4) Sixteen (16’) ft. Enclosed Aluminum Trailers – PATH

Note: These services may be federally funded in whole or in part
54783 09-Nov-2018

Four (4) Trailer-Mounted Diesel Pumps and Trailers: Two (2) Standard and Two (2) Custom Trailers - PATH

Note: These services may be federally funded in whole or in part
55161 09-Nov-2018

Supply and Deliver Runway Friction Testers – Central Automotive Division (CAD)

55028 08-Nov-2018

Electrical Maintenance Work Order Requirements Contract for Port Authority Facilities Located in New York – Three (3) Year Contract Period

55038 07-Nov-2018

Accident Management and Vehicle Repair Services – Two (2) Year Requirements Contract

54841 01-Nov-2018

Supply and Deliver After-Market Car and Truck Parts and Accessories Two (2) Year Requirements Contract

54832 25-Oct-2018

Supply and Deliver Chevron Springs as manufactured by Kawasaki Rail Car, Inc. or Vulcanite for PATH PA-5 Railcars

54319 24-Oct-2018

Supply and Deliver Material Carts – PATH. Please note: It is anticipated that this solicitation and the resulting purchase order may be funded in whole or in part by a grant from the Federal Transit Administration (FTA). Accordingly, this solicitation and the resulting contract are subject to applicable FTA requirements

54851 24-Oct-2018

Refuse Removal, Recycling and Disposal Services at Port Authority Trans-Hudson (PATH) Facilities Located in New Jersey – Two (2) Year Contract

54291 24-Oct-2018

Inspection, Testing and Maintenance of the Fire Protection and Life Safety Systems at John F. Kennedy International Airport - Two (2) Year Contract

54758 18-Oct-2018

Call-In Plumbing, Maintenance, Inspection and Repair Services at Newark Liberty International Airport (EWR)

54516 17-Oct-2018

Removal of Rubber Deposits from Runways at John F. Kennedy International, Newark Liberty International, LaGuardia, Stewart International and Teterboro Airports – Two (2) Year Requirements Contract

54257 16-Oct-2018

Maintenance and Repair Services Contract for Diesel Generators at Port Authority Trans-Hudson (PATH) Facilities, Jersey City, New Jersey

54630 16-Oct-2018

Building General Maintenance, Repairs and Construction on a Work Order Basis at the Port Authority Teleport in Staten Island, New York and Bathgate Industrial Park in Bronx, NY-Two Year Contract

54556 15-Oct-2018

Supply and Deliver Path Rail Name Plates

54530 11-Oct-2018

Supply and Deliver Lighting Equipment and Accessories, as Manufactured by Luminator Mass Transit, LLC, for PATH NJ locations. Two (2) Year Requirements Contract

54360 09-Oct-2018

Manufacture, Supply and Deliver Turnout Parts for Grove Street, Hoboken, 33rd Street and Westside Interlockings for PATH

54676 05-Oct-2018

Re-Bid - Medical Waste Removal and Disposal Services for Various Port Authority Facilities Located in New York And New Jersey – Two-Year Contract

54460 01-Oct-2018

Twenty-Eight (28) Inch Class “A” Steel Wheels for PATH PA-5 Railcars per Specification S-0002-T -Rev.3 and Drawings

 

Contract/
Solicitation
Bid Due Date Contract Title/Solicitation Description
PAT-651 13-Dec-2018

New York and New Jersey Facilities – Building and Site Improvements Via Work Order

PAT-774.176 07-Dec-2018

Harrison Car Maintenance Facility – Replacement Of HCMF Track Slab And Rehabilitation Of Parking Lots And Road Pavement

PAT-214.013 06-Dec-2018

PATH – Journal Square Transportation Center – Public Restrooms Rehabilitation

EWR-154.386 04-Dec-2018

Newark Liberty International Airport – Terminal A Redevelopment Program Airside Utilities And Paving South – Phase 2

LGA-124.269 04-Dec-2018

LaGuardia Airport - Hangar 7S Drainage Rehabilitation

BT-924.159 30-Nov-2018

Port Authority Bus Terminal - Priority Improvement Via Work Order

LGA-124.268 29-Nov-2018

LaGuardia Airport - Patrol Road Drainage Rehabilitation

MFA-924.452 20-Nov-2018

Newark Liberty International Airport and Teterboro Airport – Disposal of Construction Debris, Contaminated And Hazardous Materials Via Work Order

EWR-154.299 15-Nov-2018

Newark Liberty International Airport – Replacement of Central Heating and Cooling Plant (CHRP) North Electrical  Substation and Chiller Upgrades

WTC-500.010A 14-Nov-2018

World Trade Center - Immediate Repairs

JFK-164.020 09-Nov-2018

John F. Kennedy International Airport – Reconstruction of Runway 13L-31R And Associated Taxiways

PAT-024.200 08-Nov-2018

Path – Upgrade of Fire Supperssion System

LGA-924.120 08-Nov-2018

Laguardia Airport – Runway Instrument Landing System/Approach Lighting System Piers Priority Repairs

EWR-924.453 08-Nov-2018

Newark Liberty International Airport – General Airport Signage Via Work Order

AK-196 07-Nov-2018

Staten Island Bridges - Maintenance Pavement Repairs Via Work Order

HT-224.125 06-Nov-2018

Holland Tunnel – New York Emergency Garage Building – Parapet Repairs and Roof Replacement

PAT-774.174 01-Nov-2018

PATH – Grove Street Station Head House Permanent Flood Protection

PAT-784.175 31-Oct-2018

PATH – Extension of C-Yard Rail Bridge Over Waldo Tunnel Portal

EWR-154.306 25-Oct-2018

Newark Liberty International Airport – Rehabilitation of Runway 11-29

BT-254.153 18-Oct-2018

Port Authority Bus Terminal – Partial South Wing Third Floor Wearing Course Rehabilitation and Riding Surface Membrane

JFK-174.017 17-Oct-2018

John F. Kennedy International Airport – Replacement of 86 Pad Substation

EWR-154.398 12-Oct-2018

Newark Liberty International Airport – Terminal A Redevelopment Program Traffic/Facility Infrastructure Upgrades Via Work Order

HT-924.152 10-Oct-2018

Holland Tunnel – Maintenance Pavement Repairs Via Work Order

GWB-924.168 09-Oct-2018

George Washington Bridge – Rock Slope Priority Repairs

HT-924.110 09-Oct-2018

Holland Tunnel – New Jersey Administration Building Second Means of Egress

PAT-784.169 02-Oct-2018

PATH – Exchange Place and Newport Station Head Houses Permanent Flood Protection

MFA-947.471 27-Sept-2018

Newark Liberty International Airport and Teterboro Airport – Immediate Airport

MFA-924.471 27-Sept-2018

New York Airports – Construction Management/General Contracting Services for Priority Improvements

EWR-924.470 27-Sept-2018

Newark Liberty International Airport – Construction Management/General Contracting Services for Priority Improvements

MFB-100.538 27-Sept-2018

Lincoln Tunnel and Port Authority Bus Terminal Immediate Repairs

GWB-244.204A 25-Sept-2018

George Washington Bridge – Rehabilitation of Center Avenue and Lemoine Avenue Bridges

EWR-154.348 25-Sept-2018

Newark Liberty International Airport – Replacement of Air Train Station P4 Elevator Shaft Way Enclosure Glass

PAT-784.162 13-Sept-2018

PATH – Hoboken Flood Resiliency

SWF-164.032 07-Sept-2018

Stewart International Airport – Terminal Expansion – Federal Inspection Services Facility

LT-944.096B 28-Aug-2018

Lincoln Tunnel – Replacement of Aboveground Storage Tanks

WTC-500.010 23-Aug-2018

Immediate Repairs

GWB-924.137 16-Aug-2018

George Washington Bridge – New Jersey Administration Building Sprinkler System Rehabilitation

LT-924.183 14-Aug-2018

Lincoln Tunnel – South Tube Pavement Fine Milling

GWB-244.049 07-Aug-2018

George Washington Bridge – Trans-Manhattan Expressway Median Barriers And Water System ‘C’ Rehabilitation

PN-654.562A 02-Aug-2018

Port Newark – Building 267 Roof Collapse Repair

MF-244.252 25-July-2018

Multi-Facility Bridges – Goethals Bridge and Outerbridge Crossing – Cashless Tolling Infrastructure Via Work Order

LGA-124.260 18-July-2018

LaGuardia Airport – Rehabilitation of Runway 4-22 and Associated Taxiways

HT-224.082 18-July-2018

Holland Tunnel – Replacement of Bulkhead Doors In Ventilation Buildings

LT-944.096A 28-June-2018

Lincoln Tunnel – Replacement of AboveGround Storage Tanks

PAT-774.170 13-June-2018

PATH – Replacement of Exchange Place and Newport Station Escalators and Elevators

SWF-018 07-June-2018

Stewart International Airport - Building and Sitework Via Work Order

 

Contract/
Solicitation
Bid Due Date Contract Title/Solicitation Description
WTC-500.003 17-Oct-2018

World Trade Center – General Signage Via Work Order

WTC-500.002 17-Oct-2018

World Trade Center – General Building and Site Work Via Work Order

WTC-500.001 23-Aug-2018

Site Wide Systems Integration Via Work Order

WTC-964.958A 10-July-2018

World Trade Center (WTC) Flood Mitigation and Resiliency Improvements Program –South Bathtub Water Intrusion Protection Systems – Below Grade

WTC-964.960
Bid No. 52046
5-Mar-2018

World Trade Center (WTC) - Flood Mitigation and Resiliency Improvements Program – Pumps and Water Removal Systems

Note:  The Contract may be federally funded in whole or in part by the Federal Transit Administration (FTA). Accordingly, this procurement and contract are subject to applicable FTA requirements.
WTC-964.944 10-May-2017

World Trade Center (WTC) Flood Mitigation and Resiliency Improvement Program – Vehicular Security Center Water Intrusion Protection Systems – At Grade

 


Web Site Disclaimer    |    Privacy Statement
© 2001-CurrentYear The Port Authority of New York and New Jersey. All Rights Reserved.

The Port Authority of New York and New Jersey
(212) 435-7000  •  4 World Trade Center, 150 Greenwich Street, New York, NY 10007